066/2022

Effective from 01 DEC 2022

Published on 17 NOV 2022

  Temporary Obstacles in the vicinity of ELLK

Four cranes erected at the European Investment Bank (EIB) Kirchberg at approximately 1.5 NM from ARP, BRG 250 degrees.

Crane 1:Position:493726N 0060834E
Elevation:1220 FT AMSL / 157 FT AGL
Radius:60 M
Crane 2:Position:493726N 0060832E
Elevation:1207 FT AMSL / 144 FT AGL
Radius:60 M
Crane 3:Position:493724N 0060830E
Elevation:1306 FT AMSL / 246 FT AGL
Radius:60 M
Crane 4:Position:493724N 0060827E
Elevation:1194 FT AMSL / 121 FT AGL
Radius:60 M

ICAO day and night markings installed on crane 3.

The works are estimated to be finished in August 2025.