Contact:

AIM Belgium
Control Tower
Tervuursesteenweg 303
1820 Steenokkerzeel
BELGIUM

AFS: EBVAYOYX

Email: aip.production@skeyes.be

URL: https://ops.skeyes.be

AIP Supplement Belgium and Luxembourg


SUP

021/2024

Effective from 16 MAY 2024

Published on 04 APR 2024

  EBOS - Changes to Declared Distances due to WIP

1   General

Construction works for the removal of terrain irregularities in the runway strip.

Piping of the open parts of the watercourse “Steenovengeleed” situated on both sides in the runway strip abeam TWY L.

Construction works will be performed on the following dates:

Construction works take place from MON to FRI from 0500 till 1600.

There are no restrictions outside these working hours (nights and weekend) and dates.

2   Description

There are 2 separate construction sites without interference with the runway. These are situated in the grass area “North” and grass area “South” of the runway.

The open parts of the watercourse “Steenovengeleed” in the area between 90 M and 150 M from the runway centreline will be removed.

3   Impact on Operations

The length of the runway will be shortened by 250 M so that the construction zone will be located outside the strip.

Consequently, some declared distances will be adjusted during working hours:

RWYTORA (M)TODA (M)ASDA (M)LDA (M)
082950295029502650
262950295029502785

The distances for intersection take-off on RWY 08 will also be temporarily 250 M shorter and the displayed distances on the signs at the holding position do not correspond:

RWYFrom TWYTORA (M)TODA (M)ASDA (M)
08C1151115111511
08D1182918291829
08E1203520352035
26A217821782178
26C1143814381438
26B1161016101610

4   Charts