AIP Supplement Belgium and Luxembourg


SUP

053/2023

Effective from 07 SEP 2023

Published on 24 AUG 2023

  EBLG - Renewal Concrete TWY A between S3 and S5

This AIP SUP describes the planned works and restrictions to be expected.

1   General

The renovation works will take place in 5 phases. They will begin in the fall of 2023 and be completed in the summer of 2025.

Specific timings will be announced by NOTAM.

The works will take place daily, Monday to Friday, between 0530 (0430) and 1530 (1430).

Works are dependent on meteorological conditions.

During works, near the working zone, there will be holes, motorized equipment.

Everything will be clear when TWY A reopens at the end of the works.

Works are not allowed during aerodrome LVP.

During the renovation works, the portion of TWA A impacted by the works will be completely closed. Aircraft will be diverted by the main RWY (04R/22L) and/or the contingency RWY (04L/22R).

When there are no works in progress, a deviation of TWY A will be used around the area impacted.

The deviation will be compliant for aircraft of MAX Code E (clearance=43.5 M).

On the south part of the aerodrome, the follow-me will be mandatory H24.

TWY renovation works affect ground operations at the aerodrome. Stands will be closed and/or limited according to diversion plan.

Additional information and late changes to this SUP will be announced by NOTAM.

During interruptions of the works (between each phase and/or during the winter season), it will be possible to use TWY A and apron as normal.

For more information contact:

Airport operations: apoc@liegeairport.com

Airport inspection: inspection-eblg@spw.wallonie.be

2   Works planning and impact on operations for each phase

2.2   Phase P2: between S3 and S4

2.5   Phase P5: between S4 and S5