Contact:AIM Belgium AFS: EBVAYOYX Email: aip.production@skeyes.be | AIP Supplement Belgium and Luxembourg | SUP 010/2024 Effective from 21 MAR 2024 Published on 07 MAR 2024 |
Construction works are taking place at Luxembourg Airport for the new “Skypark Business Center” building. The works are located right next to and on the western side of Terminal A.
The works have started in November 2020 and are now in phase 3.
To complete the works, four fixed cranes operate on the “Skypark” construction site.
Phase 3 has started as of mid-February 2022 and is expected to last until the end of 2024.
CRANES | LATITUDE | LONGITUDE | HEIGHT AGL (M) | HEIGHT AGL (FT) | ELEVATION AMSL (EGM 2008) (M) | JIB (M) | OLS PENETRATION (FT) |
G3 | 493801N | 0061250E | 74.50 | 244.41 | 443.74 | 56.80 | 95.00 |
G5 | 493800N | 0061245E | 66.02 | 216.58 | 435.26 | 51.80 | 67.18 |
G6 | 493759N | 0061243E | 55.67 | 182.63 | 424.91 | 41.80 | 33.22 |
G7 | 493758N | 0061241E | 74.50 | 244.41 | 443.74 | 51.80 | 95.00 |
Crane G1 has been disassembled in March 2023.
Crane G2 has been disassembled in July 2023.
Crane G4 has been disassembled in January 2024.
Cranes G6 and G7 (phase 3 of construction) are expected to be disassembled by the end of 2024.
Due to the height of the cranes, the OCA has been temporarily increased for the following IAP:
IAP | New OCA (FT) |
RNP RWY 24 LNAV/VNAV CAT D | 1617 |
RNP RWY 06 LPV CAT D | 1358 |
RNP RWY 06 LPV CAT DL | 1360 |
ILS CAT I RWY 06 CAT D | 1358 |
ILS CAT I RWY 06 CAT DL | 1360 |
LOC RWY 06 ALL CAT | 1600 |
AIP SUP 054/2023 is hereby cancelled.